University accommodation block ready for winter
A quick turn around was needed when the existing 1800KW’s of heating boilers failed along with the CHP units. Replacement boilers were installed along with a redesign and buffer to allow for future renewable technologies, the CHP was repaired by the manufacturer and the BMS system was altered and recommissioned to enable the system to work correctly and efficiently.